logo
products

Towing Tractor Drive Mobile Asphalt Batch Mixing Plant With Wearable Blade

Basic Information
Certification: CE/CNAS/SGS/ISO
Model Number: QLB-Y
Minimum Order Quantity: 1 set
Price: negotiation
Packaging Details: Nude Packing
Delivery Time: negotiation /3 month after received your payment
Payment Terms: L/C, T/T
Supply Ability: 10 sets per month
Detail Information
Moving Type: Chassis On Wheel Belt Width: 600mm
Output: 80t/h Driven: Towing Truck
Noise: ≤70DB Attitude: ≤1000M
Heating Method: Heat Transfer Oil
Highlight:

asphalt production plant

,

road making equipment


Product Description

Towing tractor drive mobile asphalt batch mixing plant with wearable blade&arm in mixer

 

QLB1000-Y Model Batch Mobile Asphalt Plant

Installation instructions

 

General description of mobile type HMA(hot mixing asphalt plant)

 

QLB-Y Model Batch Mobile Asphalt Plant is simple and speedy forced intermittent asphalt mixing plant produced by xitong technology group for asphalt pavement construction facing domestic and overseas markets. The equipment is composed of 7~8 units,installed by the crane. Installation and debugging will be finished in 6~7 days after the new equipment comes on the scene. It can work and discharge normally in less than 10 days. The equipment is composed of following units: cold aggregate supply system;drying and hoisting system;mixing tower system;powder supply system;dust collecting system;asphalt heating system;asphalt storage tank system and control system.

Towing Tractor Drive Mobile Asphalt Batch Mixing Plant With Wearable Blade

Preparation before installation of mixing plant:

Check foundation drawing and finish condition.

Check if the installation area meets the needs of construction.

Check if the supply power is 380V/50HZ(or60HZ),and of right capacity.

Check the distance from power line to control room of mixing plant.

Check the location of crane:50t crane 1 set;25t crane 1 set;

Crane operators should be in place;welding machine 1set;torch cutting device(oxygen,acetylene)1set;auxiliary worker 4~6.

Check if there is 1000kg standard weight(each 20-25kg)for checking scales.

Check completeness and intactness of unit components and corresponding spare parts.

 

Towing Tractor Drive Mobile Asphalt Batch Mixing Plant With Wearable Blade

 

Model QLB-Y1000 QLB-Y1500 QLB-Y2000
Output 80t/h (standard working condition) 120t/h (standard working condition) 160t/h (standard working condition)
Cold feeder Volume/No. 8M3/4 10M3/4 10M3/4
Agitator kettle Capacity More than 1000kg/batch More than 1500kg/batch More than 2000kg/batch
Drying Cylinder Φ1540*6800mm Φ1840*8100mm Φ2000*8860mm
Fuel type Diesel/mazut/LPG/Coal powder Diesel/mazut/LPG/Coal powder Diesel/mazut/LPG/Coal powder
Hot aggregate bin 20T/4 25T/4 25T/4
Ready product Temperature 130℃-165℃ 130℃-165℃ 130℃-165℃
Dust Collection method gravitational dust collector & Second baghouse dust collector gravitational dust collector & Second baghouse dust collector gravitational dust collector & Second baghouse dust collector
Asphalt tank capacity 20M3 30M3 30M3
Blackness of exhaust gas Ringelmann I Ringelmann I Ringelmann I
Operation room noise ≤70db(A) ≤70db(A) ≤70db(A)
Environment noise ≤80db(A) ≤80db(A) ≤80db(A)
Heat conduction oil furnace 300,000kcal/h 300,000kcal/h 500,000kcal/h
Total Installation Power ≈200kW ≈310kW 356KW

 

 

 

 

Contact Details